MS Project Deliverable #7 URL link
Important project questions
What are the project start/end dates?
The project start date is set for Tuesday March 4, 2014.
The project end date is set for Tuesday September 30, 2014.
How many days does the project last?
The project is set to last 151 days
What is the critical path?
The critical path is the longest course of the project, and also the shortest amount of time that the project can be completed. The critical path for our project is the completion of the Feasibility Analysis, Alternative Analysis, Financial Reports, Allocate Resources, Design, Construction, Testing, Implementation, Deliverable: Training Program, Close Project, Evaluate Project, and Evaluate the MOV. This route is the shortest amount of time the project can be completed in with no slack.
No, all of the resources have been leveled to ensure there was no over allocation of any resource.
Refined MOV - WSOS
Worldwide Sports Online Site is a
temporary endeavor to evaluate what features to use for their website and any
alternatives. The purpose of this evaluation is to understand all alternatives
and find the best solution to Worldwide Sports current problems. The most
important aspects of this website will be allowing customers to buy products
online and employees being able to update the inventory.
These goals will be realized
through the Worldwide Sports Online Site (WSOS) project.
The
goal of the Worldwide Sports Online Site project is to help them to become one
of the leading retailers in the sporting goods industry by:
- increasing the customer base by 40% in 24 months
- increasing sales by 50% in 24 months
- increasing inventory by 25% in 18 months
- reducing inventory shrinkage by 25% in 12 months
The MOV table lists in summary of
the measurable organizational value of Worldwide Sports Online Site.
Organizational Impact
|
Value
|
Metric
|
Time Frame
|
Customer
|
Provide more merchandise for
customers.
|
Increase inventory by 25%
Increase online shopping website
75%
|
18 months
28 months
|
Financial
|
Reduce cost inventory control by
going paperless.
|
Reduce inventory costs by 25%
|
12 months
|
Operational
|
Increase loss prevention.
|
Reduce inventory shrinkage by 25%
|
12 months
|
Social
|
Increase the number of customers
to purchase online.
|
Increase the number of customers
served online from 0 to 200.
|
12 months.
|
Table 1 WSOS- MOV
Cash Flow Table
The below table illustrates the project cash flow based on the resources completing the tasks. These cash flows are only based on the resources (employees) that complete each task. This table does not include any cost of training accommodations, meals, rent, hardware/software, etc. The project budget remains at $300,000 with everything included.
Milestone Table
The milestone report displays all of the milestones completed to date, the next ones to be completed, and any late milestones that are going over budget.
Cost Overview Table
This table shows the costs that have already happened, the cost of any late tasks, and the cost of the other remaining tasks not yet completed. Just like the resource overview table, these costs are solely the social capital (employee labor) associated with each task to be finished.
Resource Overview Table
The following 2 tables illustrate the total cost of each
resource and the standard rate of the resources used in this project. Each resource
used has a cost associated with it based on hourly pay. The costs are
represented in hourly pay as opposed to a salary in case the project runs over
schedule, this will keep the motivation high to get the project completed
instead of having a pay cap regardless of how much work is completed. Looking at
our WBS, each task has a resource allocated to it.
No comments:
Post a Comment